How long does a custom wood inlay marble floor installation take?

How long does a custom wood inlay marble floor installation take?

How long does a custom wood inlay marble floor installation take?

Custom wood inlay installation timeline: (1) Design/templating - 3-7 days; (2) Material prep - 5-10 days; (3) Subfloor prep - 2-3 days; (4) Inlay installation - 3-10 days; (5) Grouting/sealing - 2-3 days; (6) Final finishing - 2-3 days. Total: 3-5 weeks standard, 6-8 weeks for complex designs. PFM provides detailed timeline estimates after design consultation.

3-5 weeks

Standard project

6-8 weeks

Complex design

Free estimate

PFM consultation